An update from PennDOT on the $46.5 million Interstate 79 and Route 910 Wexford interchange project.
District 11 Executive Jason Zang says the bulk of that project is expected to be operational ahead of its original date in October 2027
“We expect to have the new ramps open in the spring of 2027, which is good news,” said Zang.
He says crews will continue working until winter weather halts progress, and secondary tasks like ramp removal and drainage work will wrap up by fall 2027.