Expect some serious slow downs now that construction has begun in one of the worst bottlenecks in metro Atlanta.
On Monday, The Georgia Department of Transportation started pacing traffic near the I-285/I-20 West Interchange.
Crews have started controlled blasting to put geotechnical borings in place, along with other utilities within the interior parts of the interchange along the I-285 southbound to I-20 eastbound ramp.
Each pacing operation will last about 20 minutes and between 10:30 a.m. and Noon, Monday through Thursday, and is expected to continue through the rest of the summer.
In addition to this, there will be more closures around the interchange as construction begins on the project. Here is a look at the closures:
Daytime Closures
Tuesday, July 22, through Thursday, July 24, 10:30 a.m. to 12 p.m. (Daily)
Traffic pacing operation at the following location:
I-285 southbound from South Cobb Drive (mile marker (MM) 14.8) to the I-20 Interchange (MM 10)
Nighttime Closures
Monday, July 21, through Friday, July 25, 7 p.m. to 6:30 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following location:
Six Flags Parkway from Lee Industrial Boulevard (MM 0) to South Service Road (MM 1)
Monday, July 21, through Friday, July 25, 8 p.m. to 5 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following locations:
Harwell Road from Collier Drive (MM 0) to Amhurst Drive (MM 1)
Delmar Lane from Arlington Drive (MM .05) to Harwell Road (MM 1.5)
Fairburn Road from Argus Circle (MM 1) to Fairlane Drive (MM 2)
Collier Drive from Harwell Road (MM 1) to Collier Court (MM 2)
Monday, July 21, through Friday, July 25, 8 p.m. to 5 a.m. (Nightly)
Single, right-lane, and right-shoulder closure at the following locations:
State Route (SR) 70/Fulton Industrial Boulevard southbound from Wendell Drive (MM 2) to Shirley Drive (MM 2.5)
SR 139/Martin Luther King Jr. Drive northbound from Old Gordon Road (MM 5) to Adamsville Drive (MM 6)
Monday, July 21, through Friday, July 25, 9 p.m. to 5 a.m. (Nightly)Single, right-lane, and right-shoulder closure at the following locations:
I-20 westbound from the Anderson Avenue underpass (MM 53.6) to Riverside Parkway (MM 47)
I-285 southbound from US 278/State Route 8/Donald Lee Hollowell Parkway (MM 11.8) to SR 139/Martin Luther King Jr. Drive (MM 9.6)
I-285 northbound from Cascade Road (MM 7.2) to Bolton Road (MM 12.6)
Monday, July 21, through Friday, July 25, 9 p.m. to 5 a.m. (Nightly)
Alternating, single, right-lane, and right-shoulder closure, and single, left-lane, and left-shoulder closure at the following location:
I-20 eastbound from Riverside Parkway (MM 47) to the I-285 Interchange (MM 50.5)
Monday, July 21, through Friday, July 25, 11 p.m. to 5 a.m. (Nightly)
Double, right-lane, and right-shoulder closure at the following location:
I-20 eastbound from Riverside Parkway (MM 47) to the I-285 Interchange (MM 50.5)