TOWN OF NIAGARA, N.Y. (WBEN)....Cutting edge energy technology-related projects could be headed for the Towns of Niagara and Pendleton respectively.
The Niagara County Industrial Development Agency directors, when they meet on Nov. 18, will begin their review of a pair of energy-based private sector-backed projects that, combined, represent a potential nearly $28 million investment.
Up for review:
* Investors 2590 Military Road LLC are proposing to develop an EV storage and charging complex along a vacant parcel at 2590 Military Road in the Town of Niagara.
The project carries a potential $15.47 million development price tag and could create a trio of new jobs plus a still-to-be determined construction jobs.
Construction is expected to begin in early 2027.
* Boston-based Nexamp - through its Donner Road Storage LLC affiliate - has proposed developing a solar and battery storage complex that would tie into National Grid's 13.2 kv feeder network.
The project is slated for a parcel at 5980 Donner Road in Pendleton.
Anchored by a network that includes five Tesla megapack 2XL battery units, the project is Nexcamp's first in the Buffalo Niagara region.
Construction will start next year and the complex should be ready to tie into the National Grid network by 2028's fourth quarter.
A full board vote on both projects will likely happen on Dec. 9.