Strongsville will see the rebuild and repave of Drake Rd between Howe and W130th this fall. Construction scheduled to start August 16th, last for 45 days ending on November 5th.
They'll be resurfacing and reconstructing, full depth base repairing, and installing ADA-compliant curb ramps.
Eastbound traffic will be maintained throughout construction.
Westbound traffic detoured southbound on W 130th to Boston Rd westbound, then north on Howe back to Drake.
Check out the detour HERE.
Drake Rd Rebuild/Repave In the Works

Susan Vineyard
By Joe CzekajAug 03, 2021