(WWJ) It's something thousands of Metro Detroiters have long been waiting for: I-696 is set to reopen this weekend.
The Michigan Department of Transportation said in a news release that the eastbound lanes of the freeway in Oakland County "are close to reopening sometime this weekend."
A MDOT spokesperson told WWJ that the hope is to have the eastbound freeway — which has been closed for nearly two years — completely reopened for drivers ahead of the morning commute on Monday, November 23.
As of Wednesday, MDOT's website now shows an end date of Saturday, Nov. 21 for the closure.
MDOT said punch list work remaining, including sign installation, pavement marking removal and replacement, etc., are being wrapped up this week. The work is weather dependent.
This all comes as road crews have been completely rebuilding I-696 from I-75 to the Lodge Freeway, necessitating a full stop to eastbound I-696 traffic, as part of the $275 million "Restore the Reuther" project.

To allow crews to safely remove and replace pavement markings approaching the current detour route of eastbound I-696 near M-10 and US-24 (Telegraph Road), MDOT said traffic will need to be reduced to one lane.
During this work, once traffic is east of M-10, then eastbound I-696 will reopen completely to I-75.
Drivers should expect the following:
8 a.m. - 5 p.m. Saturday, Nov. 21:
- Eastbound I-696 will have one lane open from Orchard Lake Road to M-10.
- The eastbound I-696 ramp to southbound M-10/US-24/Lahser Road will be closed.
- Southbound M-10 (Northwestern Highway) will be closed at I-696.
5 p.m. Saturday, Nov. 21 - mid-December:
- The southbound US-24 (Telegraph Road) ramp to southbound M-10 will remain closed.
- The Church Street bridge over I-696 will reopen along with one pedestrian crossing. Plaza bridge work will continue topside in 2027 to complete the park and parking lot.
- Wrap-up work will continue on the service drives for signs and retaining barrier walls.
Looking ahead: More work scheduled for 2027
Roadwork in the corridor won't wrap up completely once the eastbound freeway reopens.
MDOT announced that additional repaving work is slated for early 2027, along both eastbound and westbound I-696 between I-75 and Dequindre Road. That work includes pavement improvements, roadway rebuilding, bridge improvements and drainage structures. While there will be lane closures, MDOT plans to keep the freeway open to traffic.
More details on that phase of the project are forthcoming.
Project information is available at DrivingOakland.com.
WWJ will have all the updates on your radio: AM 950. Before you hit the road, tell your smart speaker to "play WWJ nine-fifty" or stream WWJ live on the free Audacy app of traffic updates, every 10 minutes on the 8s. >>LISTEN LIVE