Nicollet Avenue at Lake Street will open to traffic Tuesday for the first time in 50 years

A big week in Minneapolis as Nicollet Avenue is set to officially reopen to traffic on Tuesday after decades of being closed off at Lake Street.

The former Kmart location on Lake Street, which closed off Nicollet Ave. at that intersection for five decades.

(City of Minneapolis)

A big week in Minneapolis as Nicollet Avenue is set to officially reopen to traffic on Tuesday after decades of being closed off at Lake Street.

The street has been closed for nearly 50 years at the south Minneapolis intersection, and the reopening will connect Nicollet Avenue across Lake Street and the Midtown Greenway. Nicollet Ave will open to traffic this Tuesday.

The New Nicollet Avenue project will rebuild Nicollet Avenue from Lake Street to Cecil Newman Lane, which is where Nicollet began again north of the Kmart site.

That reopening will link the city's famous "Eat Street," packed with over 100 independent restaurants, international markets, and local cafes. It will also connect that section of south Minneapolis with surrounding commercial corridors, and routes toward downtown.

The road was blocked for decades by a Kmart store and parking lot. It closed in 1977 for construction, and the store opening in 1978.

The city bought the property for $8 million in 2017, paid $9 million in 2020 to buy out the lease, with plans to reopen it.

That was sped up after the city demolished the building after a major fire in late 2023.

The intersection will now transition from a car-heavy strip mall towards a more connected, mixed-use neighborhood. There are currently plans to redevelop the site to include new housing, with increased green space in an extremely busy, dense, and culturally diverse section of the city.

Plans also include new community facilities such as a Boys and Girls Club.

In Spring 2027 work on Cecil Newman Lane will continue between 1st Ave connecting into Nicollet Ave. Remaining work on Nicollet Ave will include fencing, irrigation system install, and planting. The new asphalt will also be seal coated in July 2027.

The Minneapolis Park and Recreation Board now will move into a community engagement and concept design portion of the development of a New Nicollet Park in 2028, with construction possibly beginning the following year.